Name of Village : Tumpui
 ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK)



Wage component10620000

Projected Job card472
Material component7080000




Total17700000




Admin. Cost1062000




G.Total18762000

Name of ProjectPerson days to be GeneratedName of WorkLocation         Costing               ( Rs in lakhs)PriorityRemarks
CATEGORY - A                  PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT –
Water Conservation 1000Water TankLungsum Lui                     3.7513New
1000Water TankSerthlum Lui                     3.7514New
1000Water TankHawldar Lui                     3.7515New
1000Water TankMP Lui                     3.7516New
1000Water TankHuan Lui                      3.7517New
1900Gabion WallZikpuii In bul                     7.1318New
Leipui Lui
CATEGORY - B     COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5
Improving productivity of lands4000Kuhva khurlaihMi 40 tan                  15.001New
4000Halfmoon TerraceC Zoramchhuana                  15.002New
Alphonso Lalrinkimi
C Thanliani
C Zochhuana
4000Halfmoon TerraceF Lalrinmawii                     15.003New
T Laldawngliana
VL Siama (focus)
C Roá¹­huamluaia
4000Bench TerraceLalthanmawii                     15.004New
MS Dawngliani
C Roá¹­huamluaia
Rothangi
Improving productivity of lands4000Bench TerraceLalremsangi                     15.005New
Vanlalhmuaki
K Lalengmawii
H Lalthana
4000Halfmoon TerraceR Lalengmawii                     15.006New
Vanneihpuii
Sathranga
C Lalrinchhana
2000Halfmoon TerraceC Malsawmtluangi                     7.507New
Lalbiaka
2000Bench TerraceLalromawii                     7.508New
Lalthemthiami
2000Land LevellingVanlalchhuangi                     7.509New
C Zochhuana
Promotion of fisheries2000Excavation of Pond convergence with focusC Liandailova                     7.5010New
Chawngkunga
Denghmingthanga
2000Excavation of PondLalhmangaihi                     7.5011New
Lalvensanga
2000Excavation of PondLalhmingsangi                     7.5012New
K Lalbiakdika
CATEGORY - D                             RURAL INFRASTRUCTURE
Rural Sanitation500Public Toilet / UrinalLalhlunengi In bul                     1.8819New
Community Hall
Karkawn










































Road connectivity /      Internal roads/Streets2500Cement ConcreteLalthlamuana In to YMA Chawlhbuk                     9.3820New
Kawngchung 
Kawnghnuai
Haria In to Doremi In
Side Drain and storm water drain á¹¬umpui area
Earthen RoadZakaii In to Mangkhawnglui
Bungkawn to PHE Pump House
Khan kawn to PHE Pump House
Thani In to Lalramlawmi Ram
Earthen Road( Widening)Enpari In to Karkawn
Karkawn to Medical Quarters
Step and footpath á¹¬umpui area
Disaster preparedness/ Restoration1300CulvertṬumpui area                     4.8821New
Drain with coverṬumpui area
Retainig WallTumpui Middle School
VC House hnuai
RC Zodinpuia In bul
Ngurzuani In bul
Lalthlamuana In to Sanglawmthanga In 
K. Lalnuntluanga In bul
Lalthanzuala In bul
Zakaii ram bul
Helipad hnuai
Chuangthangi In bul
Huan Lui bul

47200

                177.00


47200

                177.00

Under Labour Component 106.20000Lakhs


Under Material Component 70.80000Lakhs


OVERALL LABOUR MATERIAL RATIO in the GP in year 2021 - 2022 will be ---     60:40