Name of Village : Rengtekawn | ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK) | |||||
Wage component | 7020000 | |||||
Projected Job card | 312 | Material component | 4680000 | |||
Total | 11700000 | |||||
Admin. Cost | 702000 | |||||
G.Total | 12402000 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing (Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Water Conservation | 2000 | Water Tank | Rengtekawn area | 7.50 | 1 | New |
2000 | Tuikhur | Rengtekawn area | 7.50 | 2 | New | |
Land Development | 2000 | Land Levelling kawng | Rengtekawn area | 7.50 | 3 | New |
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Improving productivity of lands | 5000 | Kuhva khurlaih | Mi 50 tan | 18.75 | 4 | New |
5000 | Halfmoon Terrace | mimal huan | 18.75 | 5 | New | |
4000 | Bench Terrace | mimal huan | 15.00 | 6 | New | |
4000 | Land Levelling | mimal huan | 15.00 | 7 | New | |
Promotion of fisheries | 4700 | Excavation of Pond | mimal huan | 17.63 | 8 | New |
CATEGORY - D RURAL INFRASTRUCTURE | ||||||
Rural Sanitation | 500 | Public Toilet / Urinal | Rengtekawn area | 1.88 | 9 | New |
Road connectivity / Internal roads/Streets | 1000 | Cement Concrete | Rengtekawn area | 3.75 | 10 | New |
Side Drain and storm water drain | ||||||
Earthen Road | ||||||
Step and footpath | ||||||
Disaster preparedness/ Restoration | 1000 | Culvert | Rengtekawn area | 3.75 | 11 | New |
Retainig Wall | Rengtekawn area | |||||
31200 | 117.00 | |||||
31200 | 117.00 | |||||
Under Labour Component | 70.20000 | Lakhs | ||||
Under Material Component | 46.80000 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2021 - 2022 will be --- 60:40 |