Bairabi North AAP
| Name of Village : Bairabi North | ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK) |
|
|
| Wage component | 1,79,10,000.00 |
|
|
| Projected Job card | 796 |
| Material component | 1,19,40,000.00 |
|
|
|
|
| Total | 2,98,50,000.00 |
|
|
|
|
| Admin. Cost | 17,91,000.00 |
|
|
|
|
| G.Total | 3,16,41,000.00 |
|
|
| Name of Project | Person days to be Generated | Name of Work | Location | Costing (Rs in lakhs) | Priority | Remarks |
|
| CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – |
| Water Conservation | 100 | Water Tank | Near Lalhliri In | 10 | 1 | New |
| 100 | Near Laldinga In | 10 | 2 | New |
| 100 | PHC tlang | 10 | 3 | New |
| 100 | Bazar bul | 10 | 4 | New |
| Land Development | 7960 | Halfmoon terrace | Mimal ramah | 17.91 | 5 | New |
| 7960 | Mimal ramah | 17.91 | 6 | New |
| 7960 | Mimal ramah | 17.91 | 7 | New |
| 3980 | Mimal ramah | 8.955 | 8 | New |
| 7164 | Mimal ramah | 16.119 | 9 | New |
| CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 |
| Improving productivity of lands | 11144 | Khurlaih | mimal ramah | 25.074 | 10 | New |
| 7960 | mimal ramah | 17.91 | 11 | New |
| Promotion of fisheries | 11144 | Excavation of Pond | Mimal huan 8 ah | 25.074 | 12 | New |
| 3980 | Mimal huan 2 ah | 8.955 | 13 | New |
| 3980 | Mimal huan 2 ah | 8.955 | 14 | New |
| 3980 | Mimal huan 2 ah | 8.955 | 15 | New |
| 2388 | Mimal huan 1 ah | 5.373 | 16 | New |
| CATEGORY - D RURAL INFRASTRUCTURE: |
| Road connectivity / Internal roads/Streets | 600 | Cement Concrete | FCI godown to Synod veng | 60 | 17 | New |
| Zohlun veng to UPC Church |
| Chhinga In to SBI |
| Rimawi veng to Zahawma In |
| NH 154 to ICI veng |
| Thlanmual kawng |
| Disaster preparedness/ Restoration | 100 | Retainig Wall | Rohlupuii In bul | 19.4 | 18 | New |
|
|
|
|
|
|
|
| 79600 |
|
| 298.50 |
|
|
| 79600 |
|
| 298.50 |
|
|
| Under Labour Component | 179.10000 | Lakhs |
|
|
|
| Under Material Component | 119.40000 | Lakhs |
|
|
|
| OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be --- 60:40 |
|
|
|