Name of Village : Bilkhawthlir North ANNUAL ACTION PLAN 2020 - 2021 (BILKHAWTHLIR RD BLOCK)



Wage component11710500

Projected Job card555
Material component7807000




Total19517500




Admin. Cost1171050




G.Total20688550

Name of ProjectPerson days to be GeneratedName of WorkLocationCosting                          ( Rs in lakhs)PriorityRemarks
CATEGORY - A                  PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT –
Drought Proofing2775Road / Canal Side PlantationNH 306 sirah5.8552511New
Traditional Water Bodies30DesiltingKharzawl tuikhur7.512New
30Lungzawn
40Pa Nghanka tuikhur
Land development4440Land levellingVC ram,Kharzawl9.36841New
VC ram cheithat
CATEGORY - B     COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5
Improving productivity of lands7770Halfmoon terraceMimal huanah 1                16.392New
Mimal huanah 2
Mimal huanah 3
Mimal huanah 4
7770Halfmoon terraceMimal huanah 1                16.393New
Mimal huanah 2
Mimal huanah 3
Mimal huanah 4
5550Halfmoon terraceMimal huan 1             11.714New
Mimal huan 2
Mimal huan 3
5550Halfmoon terraceMimal huan 1             11.715New
Mimal huan 2
5550Halfmoon terraceMimal huan 1             11.716New
Mimal huan 2
2775Halfmoon terraceMimal huan 1                   5.867New
Mimal huan 2
Promotion of fisheries5550Excavation of PondMimal huan 1                11.718New
Mimal huan 2
Mimal huan 3
Mimal huan 4
Mimal huan 5
Mimal huan 6
Mimal huan 7
4995Excavation of PondMimal huan 1                10.549New
Mimal huan 2
Mimal huan 3
Mimal huan 4
Mimal huan 5
Mimal huan 6
2775Excavation of PondMimal huan 1                5.8610New
Mimal huan 2
CATEGORY - D                             RURAL INFRASTRUCTURE
Road connectivity /   Internal roads/Streets400Cement ConcreteRS Lalremmawia In to Lalthanpuii In             16.0013New
Zodinsanga In to BKT high school
SA Hall kawnveng to Hriata kawmthlang
Famkimi In to Rosiama In
Lalthanga In to Anganwadi centre
Lalhmuakliana In to Rescue centre Kharzawl
NH 306 to Daplei
Centenary road to Lunghnema In
200C onstn. Of StepsRosiama In to Lungtiawia In                5.5014New
Tuithaveng tuikhur to Liani In
Liankunga In to Hrangchhuana In
Anganwadi centre no VII to Lalengmawia In
Disaster preparedness/ Restoration200Retainig WallPlayground ah             34.0715New
Thankhuma In bulah
Lalnunzira Inbulah
200Const. of Storm Water DrainsTuithavengah                15.0016New
Kharzawlah
Panglui ah

55500

           195.18


55500

           195.18

Under Labour Component 117.10500Lakhs


Under Material Component 78.07000Lakhs


OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be ---     60:40