Name of Village : Electric veng | ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK) | |||||
Wage component | 5490000 | |||||
Projected Job card | 244 | Material component | 3660000 | |||
Total | 9150000 | |||||
Admin. Cost | 549000 | |||||
G.Total | 9699000 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Water Conservation | 2000 | Kawr khuah | Electric veng area | 7.50 | 1 | New |
2000 | Individual water tank | Laltlanthangi | 7.50 | 2 | New | |
Vanlalhruaii | ||||||
Saithangkimi | ||||||
Lalá¹anpuia | ||||||
Lalthansanga Sailo | ||||||
Lalchatuana | ||||||
Thangluaia | ||||||
Sainguri Sailo | ||||||
Lalhmachhuani | ||||||
V Lalhruaimawia | ||||||
1700 | Farm Pond | Vanlalhmuaki | 6.38 | 3 | New | |
C Lalengliana | ||||||
Lalá¹anpuia | ||||||
V Lalhruaimawia | ||||||
K Thangluaia | ||||||
Sailova | ||||||
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Improving productivity of lands | 4000 | Kuhva khurlaih | 15.00 | 4 | New | |
4000 | Halfmoon Terrace | Tlanthangi huan gosen | 15.00 | 5 | New | |
Emmanuela huan zotui zau | ||||||
Ricky Zothansanga huan | ||||||
Sainguri Sailo huan thengphek zau | ||||||
Lalhmachhuani huan mauhak zau | ||||||
4000 | Bench Terrace | C Malsawma huan Saihapui K | 15.00 | 6 | New | |
Tlanthangi huan sesih zau | ||||||
Lalhmachhuani huan mauhak zau | ||||||
Laltlanthanga Sailo huan hmawngkhawthlir | ||||||
Sainguri Sailo huan thengphek zau | ||||||
Teteii huan serlui | ||||||
Mazuali huan rengtekawn | ||||||
Denesa huan rengtekawn | ||||||
R Lalsiamliana huan | ||||||
Ricky Zothansanga huan | ||||||
500 | Nursery | Lalá¹anpuia huan | 1.88 | 7 | New | |
Tetei huan | ||||||
Promotion of Livestock | 200 | Ran Insak | Teteii | 0.75 | 8 | New |
Ropuii | ||||||
Asangi | ||||||
Hruaii | ||||||
Lallawmkima | ||||||
V Lalhruaimawia | ||||||
Luahpuii | ||||||
Lalbiaktluangi | ||||||
Lalrempuii | ||||||
Lalhmangaihzuali | ||||||
Lalzamliani | ||||||
B Vanlawma | ||||||
Lalchatuana | ||||||
Lalbiakchhunga | ||||||
Vanlaltluangi | ||||||
Sailova | ||||||
Vanlalchhuangi | ||||||
R Laldingngheti | ||||||
Shanti | ||||||
Thazuala | ||||||
Vanlalawia | ||||||
Tamanga | ||||||
Lalá¹hakima | ||||||
Lalhmingá¹hai | ||||||
K Thangluaia | ||||||
Lalnuntluangi | ||||||
Promotion of fisheries | 2000 | Excavation of Pond | Tlanthangi huan | 7.50 | 9 | New |
Zeli huan | ||||||
Buati huan | ||||||
C Lalengliana huan | ||||||
Ngaia huan | ||||||
Sepa huan | ||||||
J Zodinsanga huan | ||||||
C Lalá¹hakimi huan | ||||||
Zosanga huan | ||||||
Sainguri Sailo huan | ||||||
Zosanga huan | ||||||
R Lalsiamliana huan | ||||||
Lalhmachhuani huan | ||||||
PC Lalnunhlimi huan | ||||||
Lalngaizuali huan | ||||||
CATEGORY - D RURAL INFRASTRUCTURE | ||||||
Rural Sanitation | 500 | Tui chhe paihna | Electric veng area | 1.88 | 10 | New |
Road connectivity / Internal roads/Streets | 2500 | Cement Concrete | Rintluanga in to kawngthar 110X3m | 9.38 | 11 | New |
Vanlalhmuaki in to Zohminga in 80X3m | ||||||
R Lalsiamliana in to PC Mama in 70X3m | ||||||
Thangchhuana in to Chawngthankima in 140X3m | ||||||
Side Drain and storm water drain | Electric veng area | |||||
Earthen Road Extension | Electric veng area | |||||
Footpath | PCI to Fire dept ram 100X1.5m | |||||
Electric veng area | ||||||
Step | Kohhran Thianghlim Biak In panna 50X1.5m | |||||
Lalchatuana in to Thari in 60X1.5m | ||||||
Disaster preparedness/ Restoration | 1000 | Culvert | YMA Bungraw dahna bul 6X2.5m | 3.75 | 12 | New |
Thangluaia in bul 6X1.5m | ||||||
Community Hall bul | ||||||
Quarry lui | ||||||
Retainig Wall | Hall bul 30X2.5m | |||||
Duhawma in bul 20X3m | ||||||
Electric veng area | ||||||
24400 | 91.50 | |||||
24400 | 91.50 | |||||
Under Labour Component | 54.90000 | Lakhs | ||||
Under Material Component | 36.60000 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2021 - 2022 will be --- 60:40 | ||||||