Name of Village : Saidan
 ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK)



Wage component4432500

Projected Job card197
Material component2955000




Total7387500




Admin. Cost443250




G.Total7830750

Name of ProjectPerson days to be GeneratedName of WorkLocation         Costing         (Rs in lakhs)PriorityRemarks
CATEGORY - A                  PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT –
Water Conservation 1000Tuikhur siamH Lalropuia in bul saidan vengthar                    3.751New
Bawngpu Lui PS X bul
Ngaihchungi in bul
Pawla in bul
Benjamina in bul
2500Rain water harvesting structureSaidan area                    9.382New
Drougth Proofing200Roadside plantationSaidan area                    0.753New
CATEGORY - B     COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5
Improving productivity of lands2000khurlaihfor 23 nos of  focus benificiaries                    7.504New
3000Halfmoon TerraceHD Lalawmpuia JCN 246 rengtelui 1500nos                  11.255New
Vanlalpeki JCN 619 Zotui zau 2000nos
Neihsanga JCN 199 rengte tlangsang 800nos
Lalrinmawia JCN 229 keicham 2800nos
Vanlalfeli JCN 581 Zanlawn vengchung 1000nos
Laldingliana JCN 232 Lahmuntlang 600nos
Lalneihliana JCN 346 rengtelui 2500nos
Lalchhandama JCN 216 pharitlang 1600nos



































Improving productivity of lands3000Bench TerraceHD Lalawmpuia JCN 246 rengtelui 2000m                  11.256New
Vanlalpeki JCN 619 Zotui zau 2500m
C Siamkunga JCN 301 khamhnuai 1500m
Hauthangpuii JCN 561 pharitlang 1000m
Malsawmkima JCN 220 rengtelui 1500m
Laldingliana JCN 232 Lahmuntlang 600m
H Thangluaia JCN 236 thinglubul 1000m
1500WRC Land LevellingVanlalpeki JCN 619 Dilzau                    5.637New
Promotion of fisheries2000Excavation of Pond convergence with focusMalsawmkima JCN 220 rengtelui                     7.508New
Thangzuala JCN 235 rengtelui
Hmingthanzauva JCN 200 Saihapui
Thanseii JCN 274 rengtelui
Lalthlamuana JCN 241 rengtelui
800Excavation of Pond convergence with Fisheries DeptLalchangliana JCN 239 thinglubul                    3.009New
Thangzuala JCN 235 rengtelui
2000Excavation of PondLalzarliani JCN 267 sekahtlang                    7.5010New
Vanlalpeki JCN 619 zotui lui
Robert Lalchhuanawma JCN 209 sekahtlang
Lalá¹­anpuii JCN 484 sekahtlang
Lalneihliana JCN 346 rengtelui 
Lalremliani JCN 361 Lahmuntlang
H Thangluaia JCN 236 thinglubul 
Lalrinngheti JCN 283 saisih zau
Ngaihchhungi JCN 228 rengtelui
H Lalchangliana JCN 239 thinglubul
Promotion of Livestock100Pig styAlex Zohmingthanga JCN 279                    0.3811New



































CATEGORY - D                             RURAL INFRASTRUCTURE
Rural Sanitation100Public Toilet / UrinalCommunity Hall                    0.3812New
AWC No X
Road connectivity /   Internal roads/Streets900Cement ConcreteZoramthara in to Tuikhur via Hrangkhuma in 175X3m                    3.3813New
H Zoramlawma in to Sericulture farm 215X4m
Lainzalama in tuikhur ngaihchhungi in bul 67X3m
Khumzaliana in to VL Siama in 457X3m 
Lianmawia in to RMSA via PS X 165X4m
Laltlanliana in to Lianmawii in 230X3m
RK Lianzuala in to Benjamina in 234X3.5m
Side Drain and storm water drain Vanlalduhi in to C Siamkunga in 78X0.45X0.45m
PCI to Lalzarliani in 87X0.45X0.45m
Hranglianchhunga in to J Thangzamanga in 36X0.45X0.45m
DIET Office to Lianmawii in 460X0.45X.045m
Lianmawii in to RMSA 165m
B Lianzuala in to Hmingthanzauva in 520m
RK Lianzuala in to Khumzaliana in 120m
Earthen Road( Widening)Saidan area
Step and footpath Lalbiakthanga in to C Lalrinawma in 164X3m
PC Thangnuntluanga in bul 57m
Jail tuikhur bul 67m
H Lalropuia in to Tuikhur 63m
BNRGSK bul 65m
Khumzaliana in to Thangzuala in 75m
Hranglianchhunga in to J Thangzamanga in 36m
Lalhmangaiha in bul 54m
Lalrinfela in bul 36m
AWC & BNRGSK100Renovation of BNRGSKBNRGSK                    0.3814New
AWC No XSaidan area
Disaster preparedness/ Restoration500CulvertVL Siama in bul1.5X4m                    1.8815New
Zothanpara in bul 1.5X4m
Lalzarliani in bul 1.5X4m
Lalrinmawia in bul 1.5X4m
Retainig WallPCI bul 78X2.5m
DIET Office to Lianmawii in 460X2.5m
MS Dawngliana in bul 357X3m
Lalnuntluangi in to RK Lianzuala in 325X2.5

19700

                  73.88


19700

                  73.88

Under Labour Component 44.32500Lakhs


Under Material Component 29.55000Lakhs


OVERALL LABOUR MATERIAL RATIO in the GP in year 2021 - 2022 will be ---     60:40