Name of Village :Saihapui K | ANNUAL ACTION PLAN 2021- 2022 (BILKHAWTHLIR RD BLOCK) | |||||
Wage component | 35,77,500.00 | |||||
Projected Job card | 159 | Material component | 23,85,000.00 | |||
Total | 59,62,500.00 | |||||
Admin. Cost | 3,57,750.00 | |||||
G.Total | 63,20,250.00 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Traditional Water Bodies | 200 | Renovation | Field veng tuikhur | 5 | 1 | New |
Seiril lui tuikhuah | ||||||
Land Development | 1590 | Bench Terracing | Mimal ramah | 3.5775 | 2 | New |
1590 | Mimal ramah | 3.5775 | 3 | New | ||
1590 | Halfmoon terrace | Mimal ramah | 3.5775 | 4 | New | |
1590 | Mimal ramah | 3.5775 | 5 | New | ||
795 | Mimal ramah | 1.78875 | 6 | New | ||
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Promotion of fisheries | 2226 | Excavation of Pond | Mimal ramah | 5.0085 | 7 | New |
1431 | Mimal ramah | 3.21975 | 8 | New | ||
795 | Mimal ramah | 1.78875 | 9 | New | ||
795 | Mimal ramah | 1.78875 | 10 | New | ||
795 | Mimal ramah | 1.78875 | 11 | New | ||
CATEGORY - D RURAL INFRASTRUCTURE: | ||||||
Road connectivity / Internal roads/Streets | 2703 | Earthen road | Sumsi lui zau panna | 6.08175 | 12 | New |
Thingchuang zau panna | ||||||
200 | PCC flooring | Field veng tuikhur chung | 5 | 13 | New | |
Thlanmual kawng siam that | ||||||
100 | Small Bridge | Tui lakna lui | 5.85 | 14 | New | |
Disaster preparedness/ Restoration | 100 | Retaining wall | Khawchhungah | 5 | 15 | New |
100 | Step | Tlangveng panna | 3 | 16 | New | |
15900 | 59.63 | |||||
15900 | 59.63 | |||||
Under Labour Component | 35.77500 | Lakhs | ||||
Under Material Component | 23.85000 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be --- 60:40 |