Project Veng AAP
| Name of Village : Project Veng |
| ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK) |
|
|
| Wage component | 7177500 |
|
|
| Projected Job card | 319 |
| Material component | 4785000 |
|
|
|
|
| Total | 11962500 |
|
|
|
|
| Admin. Cost | 717750 |
|
|
|
|
| G.Total | 12680250 |
|
|
| Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
|
| CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – |
| Water Conservation | 3000 | Tuikhur | Forest tuikhur | 11.25 | 1 | New |
| Serṭawl lui tuikhur |
| Huanlui tuikhur |
| 1300 | Plantation | Project veng area | 4.88 | 2 | New |
| CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 |
| Improving productivity of lands | 4000 | khurlaih | mi 30 tan | 15.00 | 3 |
|
| 4000 | Halfmoon Terrace | mi 30 tan | 15.00 | 4 | New |
| 4000 | Bench Terrace | mi 30 tan | 15.00 | 5 | New |
| 5000 | Land Levelling | WRC mi 20 tan | 18.75 | 6 | New |
| SSB tlang |
| Biakthanga in to MS Tluangi in NREGS Road |
| LC P/S kawt |
| College veng to Lianmawia in |
| Promotion of fisheries | 3000 | Excavation of Pond convergence with focus | T Lalnunmawii | 11.25 | 7 | New |
| Vanlalhluta |
| Lalrinchhana |
| 3100 | Excavation of Pond | mi 30 tan | 11.63 | 8 | New |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| CATEGORY - D RURAL INFRASTRUCTURE |
| Road connectivity / Internal roads/Streets | 2000 | Cement Concrete | Kolasib Stadium to Hall | 7.50 | 9 | New |
| Huanlui tuikhur to Serṭawk tuikhur |
| V Sangmawia in to Huanlui tuikhur |
| SO Qtrs to LC P/S |
| Footpath | DRDA Office to PCI |
| Mary in to YMA Library |
| Step | Rohluma in bul |
| HC Vanbela in bul |
| NGO Building bul |
| Disaster preparedness/ Restoration | 2500 | Culvert | Malsawmtluangi te in peng | 9.38 | 10 | New |
| Sub Station Gate bul |
| Drain | Exchange kual |
| Zanghaki in to Saikapi in |
| DAO Qtrs to MJA Office |
| Retainig Wall | NGO Building to PCI |
| Parmawia in to Merry in |
| Lalmuankima in to Daniala Ralte in |
| 31900 |
|
| 119.63 |
|
|
| 31900 |
|
| 119.63 |
|
|
| Under Labour Component | 71.77500 | Lakhs |
|
|
|
| Under Material Component | 47.85000 | Lakhs |
|
|
|
| OVERALL LABOUR MATERIAL RATIO in the GP in year 2021 - 2022 will be --- 60:40 |
|
|
|