Name of village : Saihapui V | ANNUAL ACTION PLAN 2021 - 2022 (BILKHAWTHLIR RD BLOCK) | |||||
Wage component | 13,72,500.00 | |||||
Projected Job card | 61 | Material component | 9,15,000.00 | |||
Total | 22,87,500.00 | |||||
Admin. Cost | 1,37,250.00 | |||||
G.Total | 24,24,750.00 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Traditional water body | 100 | Tuikhur siam | Lallawmthangate tuikhur | 2.15 | 1 | New |
Tlangveng tuikhur | ||||||
Land Development | 1037 | Khur laih | Mimal ramah | 2.33325 | 2 | New |
2379 | Halfmoon terrace | Laldawngliana | 5.35275 | 3 | New | |
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Promotion of fisheries | 305 | Renovation of fish pond | Mimal ramah | 0.68625 | 4 | New |
854 | Sangha dil khuah | Mimal ramah | 1.9215 | 5 | New | |
CATEGORY - D RURAL INFRASTRUCTURE: | ||||||
Road connectivity / Internal roads/Streets | 900 | PCC flooring | Lallawmthanga In to MS Dawngliana In | 7 | 6 | New |
Thangliana In to Mangkhawng mual | ||||||
Rualthankhumi In to Thangchuailova In | ||||||
VC house to Vanlalhmuaki In | ||||||
Laltanpuia In to F Malsawma In | ||||||
Main road to Saihapui V | ||||||
Ramhmachhuana In to Lalchawimawia In | ||||||
Anganwadi centre to Lalhmachhuana In | ||||||
Rammawii In to Lalhluana In | ||||||
1525 | Kawng vur len | Saihapui V panna | 3.43125 | 7 | New | |
6100 | 22.88 | |||||
6100 | 22.88 | |||||
Under Labour Component | 13.72500 | Lakhs | ||||
Under Material Component | 9.15000 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be --- 60:40 |