Name of Village : New Diakkawn
 ANNUAL ACTION PLAN 2020 - 2021 



Wage component           97,48,200.00

Projected Job card462
Material component           64,98,800.00




Total        1,62,47,000.00




Admin. Cost             9,74,820.00




G.Total        1,72,21,820.00

Name of ProjectPerson days to be GeneratedName of WorkLocationCosting ( Rs in lakhs)PriorityRemarks
CATEGORY - A                  PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT –
Watershed Management Works5500Staggered TrenchNew Diakkawn area11.605

Water Conservation 200Water TankNew Diakkawn area5.422

Traditional Water Bodies200ExcavationNew Diakkawn area2.922

Land Development8200Bench TerracingNew Diakkawn area17.302

CATEGORY - B        COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5
Improving productivity of lands1000Farm PondNew Diakkawn area2.11

11000Land DevelopmentNew Diakkawn area23.21

Improving liveihoods through100Vermi CompostingNew Diakkawn area1.211

Promotion of livestock200Piggery ShedNew Diakkawn area4.922

100Poultry ShelterNew Diakkawn area2.011

Promotion of fisheries12700Excavation of PondNew Diakkawn area26.797

CATEGORY - D                             RURAL INFRASTRUCTURE:
Rural sanitation200Public ToiletNew Diakkawn area5.422

Road connectivity /      Internal roads/Streets500Cement Concrete flooringNew Diakkawn area6.055

300FootpathNew Diakkawn area4.633

500Boulder flooringNew Diakkawn area8.055

500Slab CulvertNew Diakkawn area9.055

Road connectivity /   Internal roads/Streets4000MittiMurram RoadNew Diakkawn area8.44

Play fields200Football, Volley Ball Court etcNew Diakkawn area0.422

Disaster preparedness/ Restoration200Const. of Storm Water DrainsNew Diakkawn area5.6120067

200Retainig WallNew Diakkawn area5.422

200Gabian WallNew Diakkawn area6.422

Construction of bulding200CrematoriumNew Diakkawn area5.422


46200

                          162.47


46200

                          162.47

Under Labour Component 
97.48200Lakhs


Under Material Component 
64.98800Lakhs


OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be ---     60:40