Name of Village : Diakkawn | ANNUAL ACTION PLAN 2020 - 2021 | |||||
Wage component | 1,86,52,400.00 | |||||
Projected Job card | 884 | Material component | 1,24,34,933.33 | |||
Total | 3,10,87,333.33 | |||||
Admin. Cost | 18,65,240.00 | |||||
G.Total | 3,29,52,573.33 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Watershed Management Works | 8600 | Staggered Trench | Diakkawn area | 18.146 | ||
Water Conservation | 200 | Check Dam | Diakkawn area | 3.422 | ||
200 | Water Tank | Diakkawn area | 20.422 | |||
Irrigation | 200 | irrigation canals | Diakkawn area | 1.422 | ||
Traditional Water Bodies | 200 | Excavation | Diakkawn area | 2.922 | ||
Land Development | 16500 | Bench Terracing | Diakkawn area | 34.815 | ||
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Improving productivity of lands | 1000 | Farm Pond | Diakkawn area | 2.11 | ||
17710 | Land Development | Diakkawn area | 37.3681 | |||
Improving liveihoods through | 100 | Vermi Composting | Diakkawn area | 1.211 | ||
Promotion of livestock | 200 | Piggery Shed | Diakkawn area | 4.922 | ||
100 | Poultry Shelter | Diakkawn area | 2.011 | |||
Promotion of fisheries | 35690 | Excavation of Pond | Diakkawn area | 75.3059 | ||
CATEGORY - D RURAL INFRASTRUCTURE: | ||||||
Rural sanitation | 200 | Drainage Channel | Diakkawn area | 20.422 | ||
Road connectivity / Internal roads/Streets | 1000 | Cement Concrete flooring | Diakkawn area | 12.11 | ||
300 | Cross Drainage | Diakkawn area | 3.633 | |||
500 | Slab Culvert | Diakkawn area | 9.055 | |||
200 | InterLocking Cement Block Road | Diakkawn area | 10.422 | |||
Road connectivity / Internal roads/Streets | 4500 | MittiMurram Road | Diakkawn area | 9.495 | ||
200 | Village Drain | Diakkawn area | 2.422 | |||
Play fields | 200 | Football, Volley Ball Court etc | Diakkawn area | 0.422 | ||
Disaster preparedness/ Restoration | 200 | Const. of Storm Water Drains | Diakkawn area | 10.4220067 | ||
200 | Retainig Wall | Diakkawn area | 11.122 | |||
200 | Gabian Wall | Diakkawn area | 17.272 | |||
88400 | 310.87 | |||||
88400 | 310.87 | |||||
Under Labour Component | 186.52400 | Lakhs | ||||
Under Material Component | 124.34933 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be --- 60:40 |