Name of Village : Vengthar | ANNUAL ACTION PLAN 2020 - 2021 (NAME OF BLOCK) | |||||
Wage component | 1,25,33,400.00 | |||||
Projected Job card | 594 | Material component | 83,55,600.00 | |||
Total | 2,08,89,000.00 | |||||
Admin. Cost | 12,53,340.00 | |||||
G.Total | 2,21,42,340.00 | |||||
Name of Project | Person days to be Generated | Name of Work | Location | Costing ( Rs in lakhs) | Priority | Remarks |
CATEGORY - A PUBLIC WORKS RELATING TO NATURAL RESOURCES MANAGEMENT – | ||||||
Watershed Management Works | 860 | Staggered Trench | Vengthar area | 1.8146 | ||
Water Conservation | 400 | Water Tank | Vengthar area | 5.844 | ||
Traditional Water Bodies | 200 | Excavation | Vengthar area | 2.922 | ||
Land Development | 17240 | Bench Terracing | Vengthar area | 36.3764 | ||
CATEGORY - B COMMUNITY ASSETS OR INDIVIDUAL ASSETS FOR VULNERABLE SECTIONS (ONLY FOR HOUSEHOLDS IN PARAGRAPH 5 | ||||||
Improving productivity of lands | 1000 | Farm Pond | Vengthar area | 2.11 | ||
8600 | Land Development | Vengthar area | 18.146 | |||
Development of fallow/waste lands | 5000 | Development of Waste / Fallow Land | Vengthar area | 10.55 | ||
Promotion of livestock | 200 | Piggery Shed | Vengthar area | 4.922 | ||
100 | Poultry Shelter | Vengthar area | 2.011 | |||
Promotion of fisheries | 18600 | Excavation of Pond | Vengthar area | 39.246 | ||
CATEGORY - D RURAL INFRASTRUCTURE: | ||||||
Rural sanitation | 200 | Drainage Channel | Vengthar area | 6.702 | ||
Road connectivity / Internal roads/Streets | 1000 | Cement Concrete flooring | Vengthar area | 19.01 | ||
500 | Slab Culvert | Vengthar area | 9.055 | |||
Road connectivity / Internal roads/Streets | 4500 | MittiMurram Road | Vengthar area | 9.495 | ||
Play fields | 200 | Football, Volley Ball Court etc | Vengthar area | 0.422 | ||
Disaster preparedness/ Restoration | 200 | Const. of Storm Water Drains | Vengthar area | 16.422 | ||
200 | Retainig Wall | Vengthar area | 15.422 | |||
200 | Gabian Wall | Vengthar area | 8.422 | |||
59400 | 208.89 | |||||
59400 | 208.89 | |||||
Under Labour Component | 125.33400 | Lakhs | ||||
Under Material Component | 83.55600 | Lakhs | ||||
OVERALL LABOUR MATERIAL RATIO in the GP in year 2020 - 2021 will be --- 60:40 |